Notice is hereby given by An Bord Pleanála (the Board) under article 112 of the Planning and Development Regulations 2001 that an environmental impact statement (EIS) has been received by the Board in accordance with section 128 of the Planning and Development Act 2000, in respect of the appeallistedin the Schedule below.

The EIS of the appeal is available for inspection and purchase during office hours at the offices of the relevant local planning authority and the Board.

Submissions or observations may be made to the Board in relation to the appeallisted in the Schedule and should be received by the Board not later than four weeks beginning on the date of publication of this notice i.e. by 5.30 p.m. on Tuesday the 29th of April, 2008. Submissions or observations must be accompanied by a fee of €50 except in the case of certain bodies specified by the Board.

Schedule

Location: Tromman, Rathmoylon, Co. Meath

Development: Extension of existing quarry, demolition of 2 no. houses and existing site offices, construction of pre-cast concrete and concrete block making plants and all associated site facilities and works.

Planning Authority: Meath County Council, Abbey Mall, Abbey Road, Navan, Co. Meath.

Planning Authority Register Reference No.: TA/60629

Planning Authority Decision: To grant permission with conditions.

Applicant: Keegan Quarries Limited.

Appellants: Keegan Quarries Limited; Kilsaran Concrete; and Rathmoylon Action Group.

Appeal Reference Number: PL17.226884