Bord Pleanála Case reference: PL04.300228
Planning Authority Case Reference: 174369
Mohera Castlelyons Fermoy Co.Cork
Cork County Council
Description
The development of a solar PV panel array with an export capacity of 5MV comprising approximately 19,000 photovoltaic panels on ground mounted frames within a site area of 11.0 hectares, 4 no. single storey inverter/transformer stations, 1 no. single storey DSO substation, 1 no. single storey customer substation with 1 no. communications pole attached, 1 no. single spares building, boundary security fencing, CCTV, associated electrical cabling and ducting, alteration to existing entrance to include access gates, access track and all associated ancillary development and landscaping works on land.
Case type
Planning Appeal
Decision
Grant permission with revised conditions
Date signed
29/06/2018
EIAR
No
NIS
No
Parties
-
Meridiem Renewables Mohera Ltd (Applicant)
-
Rachael Robinson (3rd Party Appellant) (Active)
History
-
29/06/2018
Grant permission with revised conditions
-
17/11/2017
Lodged