Bord Pleanála Case reference: VC10.301392
Purcellsinch, KIlkenny
Kilkenny County Council
Description
Laying of a 110kV cable and connection to an existing substation from a 100 MW Open-Cycle Gas Turbine/Battery Energy Storage System.
Case type
Pre-Application Consultation Request
Decision
Is not Strat. Infrast. Dev.
Date signed
12/07/2019
EIAR
No
NIS
No
Parties
-
Bord Gáis Energy (Applicant)
-
Bord Gáis Energy (Applicant) (Active)
-
Bord Gáis Energy (Applicant) (Active)
History
-
12/07/2019
Is not Strat. Infrast. Dev.
-
05/04/2018
Lodged