Bord Pleanála Case reference: PL18.305536
Planning Authority Case Reference: 18562
Luppan County Monaghan and across the townlands of Shanmullagh Coraghbrack Drumlester Knockabeany Drumbristan Tonintlieve Cloghfin Derrykinnigh More Killybreen Killycarran Derrygola Tamlet Derrilla Tonyfinnigan Knockcor Drumdart Aghaclogha, Drumcoo W
Monaghan County Council
Description
Construction of a 38kv electricity substation, switchroom and equipment compound with palisade fence; and the installation of approximately 22km of 38kV electricity cables from proposed substation to existing substation in the townland of Lisdrumdoagh.
Case type
Planning Appeal
Decision
Annulled
Date signed
26/08/2020
EIAR
Yes
NIS
Yes
Parties
-
Coolberrin Wind Ltd (Applicant)
-
An Taisce (3rd Party Appellant) (Active)
History
-
22/03/2021
Board’s Decision quashed by Order of the High Court, New Case Number ABP-309906-21.
-
26/08/2020
Annulled
-
01/10/2019
Lodged