Bord Pleanála Case reference: PL03.317227
Planning Authority Case Reference: 23148
Fahy Beg, Fahy More N, Ballymoloney, Ballyknavin, Ballyquin More, Woodpark, Leitrim, Fahy More S, Ballybrack, Aharinaghmore, Tooreen, Aharinaghbeg, Knockdonagh, Roo E, Blackwater, Rosmadda West, Parkroe, Lacklyle, Castlebank and Ardataggle, Co. Clare
Clare County Council
Description
Development of a wind farm together with the development of an underground grid connection cable to the national grid. The development will consist of 8 wind turbines, a permanent meteorological mast, an onsite 38kV electrical substation, and all associated site works. An Environmental Impact Assessment Report (EIAR) and Natura Impact Statement (NIS) have been submitted with the application
Case type
Planning Appeal
Decision
Grant Permissions with Conditions
Date signed
06/03/2024
EIAR
Yes
NIS
Yes
Parties
-
RWE Renewables Ireland Limited (Applicant)
-
RWE Renewables Ireland Limited (1st Party Appellant) (Active)
History
-
06/03/2024
Grant Permissions with Conditions
-
30/05/2023
Lodged
Documents
-
Board Meeting Record
-