An Bord Pleanála Case reference: PL04.318734
Planning Authority Case Reference: 235947
Belvelly Port Facility, Marino (Townlands), Marino Point, Cobh, Co. Cork
Cork County Council
Description
Construction of a stationary battery energy storage system which will include 154 no. 20ft. containers and 22 no. medium voltage transformers and connection to the existing substation, 2) the construction of a new internal access road, to connect to an internal road previously permitted under application register reference: 19/6783, which will connect to an existing internal road on the Marino Point site, with access from an existing entrance on the R624, 3) heating, ventilation and air condition units and all other associated site, boundary and development works. A Natura Impact Statement has been prepared in respect of the proposed development and will be submitted to the planning authority with this application.
Case type
Planning Appeal
Decision
Refuse Permission
Date signed
19/02/2025
EIAR
No
NIS
Yes
Parties
-
Ion Renewables Limited (Applicant)
-
Ion Renewables Limited (1st Party Appellant) (Active)
History
-
19/02/2025
Refuse Permission
-
19/12/2023
Lodged