Bord Pleanála Case reference: PL29S.318795
Planning Authority Case Reference: 4057/23
Poolbeg 220kV Electrical Substation and adjacent land, Pigeon House Road, Dublin 4 on site measuring 3.6ha.
Dublin City Council
Description
Construction of Gas Insulated Switchgear Switchboard building with all associated site works. Removal of reactors and extension. NIS submitted to Planning Authority
Case type
Planning Appeal
Decision
Case is due to be decided by 08/05/2024
EIAR
No
NIS
Yes
Parties
-
EirGrid, (Applicant)
-
EirGrid, (1st Party Appellant) (Active)
History
-
04/01/2024
Lodged