Bord Pleanála Case reference: RL19.RL3503
Rhode, Co. Offaly
Offaly County Council
Description
Whether the provision of a connection between the 110kv substation of the Yellow River Windfarm granted under PA0032 and the National Grid is or is not development or is or is not exempted development
Case type
Referral
Decision
Is development and is exempted development
Date signed
18/04/2017
EIAR
No
NIS
No
Parties
-
Green Wind Energy (Wexford) Ltd. (Owner/Occupier)
-
Offaly County Council (Referrer)
-
Peter Sweetman (Owner/Occupier)
-
Peter Sweetman and Stephen Carroll and Joanne Addie (Party)
History
-
18/04/2017
Is development and is exempted development
-
02/09/2016
Lodged