An Bord Pleanála Case reference: PL19.304056
Planning Authority Case Reference: 18230
Across the townlands of Stonestown, Kilcamin, Crancreagh, Derrinlough, Clooneen, Whigsborough, Galros East, Galros West, Cush, Boolinarig Big, Conspark, Ballaghanoher, Ross and Clondallow, Co Offaly
Offaly County Council
Description
Install approximately 12.5km of 38kv electricity transmission line from the permitted (windfarm) substation in Stonestown, County Offaly to the electricity substation in Clondallow, County Offaly.
Case type
Planning Appeal
Decision
Grant permission with conditions
Date signed
28/05/2020
EIAR
Yes
NIS
Yes
Parties
-
Galetech Energy Developments Cloghan Limited (Applicant)
-
Galetech Energy Developments Cloghan Limited (1st Party Appellant) (Active)
History
-
28/05/2020
Grant permission with conditions
-
26/03/2019
Lodged