An Bord Pleanála Tagairt an cháis: PL19.304056
Cásuimhir an Údaráis Phleanála: 18230
Across the townlands of Stonestown, Kilcamin, Crancreagh, Derrinlough, Clooneen, Whigsborough, Galros East, Galros West, Cush, Boolinarig Big, Conspark, Ballaghanoher, Ross and Clondallow, Co Offaly
Comhairle Contae Uíbh Fhailí
Cur síos
Install approximately 12.5km of 38kv electricity transmission line from the permitted (windfarm) substation in Stonestown, County Offaly to the electricity substation in Clondallow, County Offaly.
Cineál Cáis
Achomharc Pleanála
Cinneadh
Grant permission with conditions
Dáta an tsínithe
28/05/2020
TMTT
Tá
RTN
Tá
Páirtithe
-
Galetech Energy Developments Cloghan Limited (Applicant)
-
Galetech Energy Developments Cloghan Limited (1st Party Appellant) (Active)
Stair
-
28/05/2020
Grant permission with conditions
-
26/03/2019
Lodged