An Coimisiún Pleanála - Case reference: PA92.323980
in the counties of Clare, Limerick, Tipperary, Offaly, Kildare, and Dublin.
Tipperary County Council
Description
Proposed Water Supply Project for the Eastern and Midlands Region
Case type
Private Development - Application
Decision
Case is due to be decided by 30/06/2026
EIAR
Yes
NIS
Yes
History
-
19/12/2025
Lodged
Documents
-
Case Documentation
- View associated documents
- Applicant Documents
- Application Documents
- 1. Statutory Documents
- 2. Planning Documents
- 1. Planning Report
- 2. SID Engineering Report
- 3. Material Contravention Statement
- 4. Consultation Report
- 5. Community Gain Proposal
- 6. Draft Abstraction Document
- 7. Planning Drawings
- 3. Environmental Documents
- Appropriate Assessment Screening
- Natura Impact Statement
- Volume 1 - Non-Technical Summary
- Volume 2 - EIAR Main Report
- Volume 3 - Environmental Assessment
- Chapter 09 Water
- Chapter 10 Soils, Geology and Hydrogeology
- Chapter 11 Agriculture
- Chapter 12 Air Quality
- Chapter 13 Climate
- Chapter 14 Population
- Chapter 15 Human Health
- Chapter 16 Landscape & Visual
- Chapter 17 Cultural Heritage
- Chapter 18 Material Assets
- Chapter 19 Resource and Waste Management
- Chapter 20 Risk of Major Accidents and Disasters
- Chapter 6 Noise & Vibration
- Chapter 7 Traffic & Transport
- Chapter 8 - Biodiversity
- Volume 4 - Summary
- Volume 5 - Drawings and Figures
- Chapter 03 Consideration of Reasonable Alternatives
- Figure-3.1-Alternative-Raw-Water-Abstraction-Sites.pdf [PDF]
- Figure-3.10-Alternative-Locations-for-BPT.pdf [PDF]
- Figure-3.11-3.14-Alternative-Booster-Pumping-Station-Sites-Overview.PDF [PDF]
- Figure-3.15-3.21-Locations-of-FCV-Sites-Overview.pdf [PDF]
- Figure-3.2-Preliminary-and-Least-Constrained-Route-Corridor.pdf [PDF]
- Figure-3.22-Proposed-and-Rejected-Compound-and-Depot-Sites.pdf [PDF]
- Figure-3.3-Route-Options-Overview.pdf [PDF]
- Figure-3.4-Pipeline-Route-Options.pdf [PDF]
- Figure-3.5-Pipeline-Route-Options.pdf [PDF]
- Figure-3.6-Pipeline-Route-Options.pdf [PDF]
- Figure-3.7-Pipeline-Route-Options.pdf [PDF]
- Figure-3.8-Initial-Areas-Considered-for-WTP-Location.pdf [PDF]
- Figure-3.9-Alternative-Locations-Considered-for-WTP-Development-within-Site-Area.PDF [PDF]
- Chapter 04 Proposed Project Description
- Figure-4.1-Overview-of-the-Proposed-Project.pdf [PDF]
- Figure-4.100-Raw-Water-Intake-and-Access-Road-Proposed-Land-Use.pdf [PDF]
- Figure-4.101-Water-Treatment-Plant-and-Access-Road-Proposed-Land-Use.pdf [PDF]
- Figure-4.102-Break-Pressure-Tank-and-Access-Road-Proposed-Land-Use.pdf [PDF]
- Figure-4.103-Booster-Pumping-Station-Proposed-Land-Use.pdf [PDF]
- Figure-4.104-Flow-Control-Valve-Proposed-Land-Use.pdf [PDF]
- Figure-4.105-Termination-Point-Reservoir-Proposed-Land-Use.pdf [PDF]
- Figure-4.106-4.184-Environmental-Masterplan.pdf [PDF]
- Figure-4.185-4.235-20-Metre-Pipeline-Corridor.pdf [PDF]
- Figure-4.2-4.60-Project-Component-Overview.pdf [PDF]
- Figure-4.61-Raw-Water-Intake-and-Pumping-Station-Proposed-Site-Layout-Plan.pdf [PDF]
- Figure-4.62-Raw-Water-Intake-and-Pumping-Station-at-Parteen-Basin-Access-Road.pdf [PDF]
- Figure-4.63-Water-Treatment-Plant-Proposed-Site-Layout-Plan.pdf [PDF]
- Figure-4.64-Water-Treatment-Plant-Access-Road-Layout-Plan-and-Cross-Section.pdf [PDF]
- Figure-4.65-Proposed-Water-Treatment-Plant-Process-Flow-Diagram.pdf [PDF]
- Figure-4.66-Break-Pressure-Tank-Site-Layout.pdf [PDF]
- Figure-4.67-Break-Pressure-Tank-Access-Road.pdf [PDF]
- Figure-4.68-Booster-Pumping-Station-Proposed-Site-Layout.pdf [PDF]
- Figure-4.69-Line-Valve-and-Flow-Control-Valve-Plan-and-Cross-Sections.pdf [PDF]
- Figure-4.70-Termination-Point-Reservoir-Proposed-Phase-1-Site-Layout.pdf [PDF]
- Figure-4.71-Termination-Point-Reservoir-Access-Road-Layout.pdf [PDF]
- Figure-4.72-Overview-of-Proposed-38kV-Uprate-Works.pdf [PDF]
- Figure-4.73-4.80-Proposed-38-kV-Uprate-Works.pdf [PDF]
- Figure-4.81-Future-Connection-Point-Valve-Detail.pdf [PDF]
- Figure-4.82-Proposed-Typical-Line-Valve-Arrangement-(Incl-2-Air-Valves).pdf [PDF]
- Figure-4.83-Proposed-Typical-Line-Valve-Arrangement-(No-Air-Valves).pdf [PDF]
- Figure-4.84-Proposed-Typical-Line-Valve-Arrangement-(Incl-1-Air-Valve-Upstream).pdf [PDF]
- Figure-4.85-Proposed-Typical-Line-Valve-Arrangement (Incl-1-Air-Valve-Downstream).pdf [PDF]
- Figure-4.86-Proposed-Typical-Air-Valve-Arrangement.pdf [PDF]
- Figure-4.87-Proposed-Typical-Washout-Valve-Arrangement.pdf [PDF]
- Figure-4.88-Typical-Line-Valve-Arrangement-(Including-Embankment-Cross-Section).pdf [PDF]
- Figure-4.89-Raw-Water-Intake-and-Pumping-Station-Proposed-Landscape-Plan.pdf [PDF]
- Figure-4.90-Raw-Water-Intake-and-Pumping-Station-Proposed-Site-Access-Road-Landscape-Plan.pdf [PDF]
- Figure-4.91-Water-Treatment-Plant-Proposed-Landscape-Plan.pdf [PDF]
- Figure-4.92-Water-Treatment-Plant-Proposed-Access-Road-Landscape-Plan.pdf [PDF]
- Figure-4.93-Break-Pressure-Tank-Proposed-Landscape-Plan.pdf [PDF]
- Figure-4.94-Break-Pressure-Tank-Proposed-Access-Road-Landscape-Plan.pdf [PDF]
- Figure-4.95-Booster-Pumping-Station-Proposed-Landscape-Plan.pdf [PDF]
- Figure-4.96-Flow-Control-Valve-Proposed-Landscape-Plan.pdf [PDF]
- Figure-4.97-Termination-Point-Reservoir-Proposed-Landscape-Plan.pdf [PDF]
- Figure-4.98-Termination-Point-Reservoir-Proposed-Access-Road-Layout-Plan.pdf [PDF]
- Figure-4.99-Landscape-Specification.pdf [PDF]
- Chapter 05 Construction & Commissioning
- Figure-5.01-Raw-Water-Intake-and-Pumping-Station-Temporary-Works-Layout.pdf [PDF]
- Figure-5.02-Water-Treatment-Plant-Indicative-Site-Compound-Plan.pdf [PDF]
- Figure-5.03-Pipe-Construction-Compound-Lisgarriff.pdf [PDF]
- Figure-5.04-Break-Pressure-Tank-Indicative-Satellite-Construction-Compound-Plan.pdf [PDF]
- Figure-5.05-Booster-Pumping-Station-Indicative-Satellite-Construction-Compound-Plan.pdf [PDF]
- Figure-5.06-Pipe-Construction-Compound-Killananny.pdf [PDF]
- Figure-5.07-Pipe-Construction-Compound-Drummond.pdf [PDF]
- Figure-5.08-Termination-Point-Reservoir-Indicative-Satellite-Construction-Compound-Plan.pdf [PDF]
- Figure-5.09-Pipe-Construction-Compound-Carrigatogher.pdf [PDF]
- Figure-5.10-Pipe-Storage-Depot-Toora.pdf [PDF]
- Figure-5.11-Pipe-Storage-Depot-Boveen.pdf [PDF]
- Figure-5.12-Pipe-Storage-Depot-Fortel.pdf [PDF]
- Figure-5.13-Pipe-Storage-Depot-Derrinboy.pdf [PDF]
- Figure-5.14-Pipe-Storage-Depot-Derryweelan.pdf [PDF]
- Figure-5.15-Pipe-Storage-Depot-Rathlumber.pdf [PDF]
- Figure-5.16-Pipe-Storage-Depot-Graiguepottle.pdf [PDF]
- Figure-5.17-Pipe-Storage-Depot-Barberstown-Upper.pdf [PDF]
- Figure-5.18-5.26-Haul-Roads.pdf [PDF]
- Figure-5.27-Typical-Construction-Working-Width.pdf [PDF]
- Figure-5.28-Typical-Construction-Working-Width-Peat.pdf [PDF]
- Figure-5.29-Water-Treatment-Plant-Construction-Sequences.pdf [PDF]
- Figure-5.30-Water-Treatment-Plant-Details-of-Entrance-at-R445.pdf [PDF]
- Figure-5.31-Damming-and-Fluming-(Typical-Arrangement).pdf [PDF]
- Figure-5.32-Damming-and-Pumping-(Typical-Arrangement).pdf [PDF]
- Figure-5.33-Typical-Trenchless-Crossing-Arrangement.pdf [PDF]
- Figure-5.34-Typical-Construction-Working-Width-Trenchless-Crossing-Launch-Pit.pdf [PDF]
- Figure-5.35-5.85-Methods-of-Construction.pdf [PDF]
- Chapter 10 Soils, Geology and Hydrogeology
- Figure-10.1-10.4 Soils.pdf [PDF]
- Figure-10.113-10.117-Landslide-Susceptibility.pdf [PDF]
- Figure-10.118-10.122-Source-Protection-Areas.pdf [PDF]
- Figure-10.123-10.134-Groundwater-Monitoring.pdf [PDF]
- Figure-10.13-Karst-and-Groundwater-Flooding.pdf [PDF]
- Figure-10.135-to-10.149-Conceptual-Site-Model.pdf [PDF]
- Figure-10.14-10.17-Groundwater-Vulnerability.pdf [PDF]
- Figure-10.150-10.162-Proposed-Bord-na-Móna-Groundwater-Monitoring-Locations.pdf [PDF]
- Figure-10.18-10.22-Soils-Geological-Heritage.pdf [PDF]
- Figure-10.23-10.81-GI-Locations.pdf [PDF]
- Figure-10.5-10.8-Subsoils.pdf [PDF]
- Figure-10.82-10.86-Potential-Contaminated-Land.pdf [PDF]
- Figure-10.87-10.91-Geomorphology.pdf [PDF]
- Figure-10.9-10.12-Geology.pdf [PDF]
- Figure-10.92-10.112-Peat-Areas.pdf [PDF]
- Chapter 11 Agriculture
- Chapter 12 Air Quality
- Chapter 14 Population
- Chapter 15 Human Health
- Chapter 16 Landscape & Visual
- Figure-16.1-Digital-Terrain-Model-Zone-of-Theoretical-Visibility-Map-Proposed-Raw-Water-Intake-&-Pumping-Station.pdf [PDF]
- Figure-16.10-Viewpoint-Locations-Selected-for-the-Proposed-Raw-Water-Intake-&-Pumping-Station.pdf [PDF]
- Figure-16.11-Viewpoint-Locations-Selected-for-the-Proposed-Water-Treatment-Plant.pdf [PDF]
- Figure-16.12-Viewpoint-Locations-Selected-for-the-Proposed-Break-Pressure-Tank.pdf [PDF]
- Figure-16.13-Viewpoint-Locations-Selected-for-the-Proposed-Booster-Pumping-Station.pdf [PDF]
- Figure-16.14-Viewpoint-Locations-Selected-for-the-Proposed-Termination-Point-Reservoir.pdf [PDF]
- Figure-16.15-Digital-Terrain-Model-Zone-of-Theoretical-Visibility-Map-Proposed-Booster-Pumping-Station.pdf [PDF]
- Figure-16.16-Digital-Surface-Model-Zone-of-Theoretical-Visibility-Map-Proposed-Booster-Pumping-Station.pdf [PDF]
- Figure-16.17-Viewpoint-Locations-Selected-for-the-Proposed-Flow-Control-Valve.pdf [PDF]
- Figure-16.2-Digital-Surface-Model-Zone-of-Theoretical-Visibility-Map-Proposed-Raw-Water-Intake-&-Pumping-Station.pdf [PDF]
- Figure-16.3-Digital-Terrain-Model-Zone-of-Theoretical-Visibility-Map-Proposed-Water-Treatment-Plant.pdf [PDF]
- Figure-16.4-Digital-Surface-Model-Zone-of-Theoretical-Visibility-Map-Water-Treatment-Plant.pdf [PDF]
- Figure-16.5-Digital-Terrain-Model-Zone-of-Theoretical-Visibility-Map-Proposed-Break-Pressure-Tank.pdf [PDF]
- Figure-16.6-Digital-Surface-Model-Zone-of-Theoretical-Visibility-Map-Proposed-Break-Pressure-Tank.pdf [PDF]
- Figure-16.7-Digital-Terrain-Model-Zone-of-Theoretical-Visibility-Map-Proposed-Termination-Point-Reservoir.pdf [PDF]
- Figure-16.8-Digital-Surface-Model-Zone-of-Theoretical-Visibility-Map-Proposed-Termination-Point-Reservoir.pdf [PDF]
- Figure-16.9-Viewpoint-Locations-Selected-for-the-38kV-Uprate-Works.pdf [PDF]
- Chapter 17 Cultural Heritage
- Chapter 18 Material Assets
- Chapter 21 Cumulative Effects and Interactions
- Chapter 6 Noise & Vibration
- Chapter 7 Traffic & Transport
- Figure-7.1-Project-Component-Overview.pdf [PDF]
- Figure-7.18-7.21-Collisions.pdf [PDF]
- Figure-7.2-7.8-Haul-Roads-(with-access-points).pdf [PDF]
- Figure-7.22-7.26-AADT-Do-Minimum-Do-Something.pdf [PDF]
- Figure-7.27-7.29-Pedestrians-and-Cyclists-for-Junctions.pdf [PDF]
- Figure-7.30-7.32-Public-Transport-for-Junctions.pdf [PDF]
- Figure-7.33-7.38-Public-Transport-or-Pedestrians-and-Cyclists-for-Road-Network.pdf [PDF]
- Figure-7.9-7.17-Traffic-Counts-overview.pdf [PDF]
- Chapter 8 Biodiversity
- Figure-8.1-European-Sites-Within-the-Potential-Zone-of-Influence-of-the-Proposed-Project.pdf [PDF]
- Figure-8.109-8.212-Protected-Fauna.pdf [PDF]
- Figure-8.2-Nationally-Designated-Sites-Within-the-Potential-Zone-of-Influence-of-the-Proposed-Project.pdf [PDF]
- Figure-8.3-Ramsar-Sites-and-Nature-Reserves-Within-the-Potential-Zone-of-Influence-of-the-Proposed-Project.pdf [PDF]
- Figure-8.4-8.108-Habitat-and-Flora-Map.pdf [PDF]
- Chapter 03 Consideration of Reasonable Alternatives
- Volume 6 - Appendices
- Chapter 1 Introduction
- Chapter 10 Soils, Geology and Hydrogeology
- Appendix-A10.1-Ground-Investigations.pdf [PDF]
- Appendix-A10.10-BPS-Ground-Investigations.pdf [PDF]
- Appendix-A10.11-Lot-3-Peatlands-TWC-10,000-to-TWD-29,000.pdf [PDF]
- Appendix-A10.12-Lot-3-Peatlands.pdf [PDF]
- Appendix-A10.13-TPR-Ground-Investigations.pdf [PDF]
- Appendix-A10.14-Supplemental-Ground-Investigations-for-Lot-3.pdf [PDF]
- Appendix-A10.15-Summary-of-Private-Groundwater-Supplies.pdf [PDF]
- Appendix-A10.16-Dewatering-Calculations.pdf [PDF]
- Appendix-A10.2-RWI-Ground-Investigations-2018-2019.pdf [PDF]
- Appendix-A10.3-Petrol-Station-Assessment.pdf [PDF]
- Appendix-A10.4-RWI&PS-Ground-Investigations-2022.pdf [PDF]
- Appendix-A10.5-RWRM-Ground-Investigations.pdf [PDF]
- Appendix-A10.6-WTP-Ground-Investigations.pdf [PDF]
- Appendix-A10.7-Lot-1-Treated-Water-Pipeline-TWO-WTP-BPT.pdf [PDF]
- Appendix-A10.8-BPT-Ground-Investigations.pdf [PDF]
- Appendix-A10.9-Lot-2-Pipeline-Ground-Investigations.pdf [PDF]
- Chapter 11 Agriculture
- Appendix-A11.1-Agronomy-Impact-Assessment-Farm-Survey.pdf [PDF]
- Appendix-A11.2-Table-of-Impact-Assessment-Pipeline-Infrastructure.pdf [PDF]
- Appendix-A11.3-Table-of-Impact-Assessment-Infrastructure-Sites.pdf [PDF]
- Appendix-A11.4-Summary-of-Land-Acquisition-Type.pdf [PDF]
- Appendix-A11.5-Table-of-Impact-Assessment-38kV-Uprate-Works.pdf [PDF]
- Chapter 12 Air Quality
- Chapter 14 Population
- Chapter 15 Human Health
- Chapter 16 Landscape & Visual
- Appendix-A16.1-Operational-Phase-Visual-Impact-Appraisal-at-Representative-View-Points.pdf [PDF]
- Appendix-A16.2-Photomontages-38kV-Uprate-Works.pdf [PDF]
- Appendix-A16.2-Photomontages-Booster-Pumping-Station.pdf [PDF]
- Appendix-A16.2-Photomontages-Break-Pressure-Tank.pdf [PDF]
- Appendix-A16.2-Photomontages-Flow-Control-Valve.pdf [PDF]
- Appendix-A16.2-Photomontages-Raw-Water-Intake-&-Pumping-Station.pdf [PDF]
- Appendix-A16.2-Photomontages-Termination-Point-Reservoir.pdf [PDF]
- Appendix-A16.2-Photomontages-Water-Treatment-Plant.pdf [PDF]
- Chapter 17 Cultural Heritage
- Appendix-A17.1a-Archaeological-Geophysical-Survey-Ballyannymore,-Ballyanny-Lower-and-Tonagh-Curralanty.pdf [PDF]
- Appendix-A17.1b-Archaeological-Geophysical-Survey-Loughtown-Upper.pdf [PDF]
- Appendix-A17.2-Plates.pdf [PDF]
- Appendix-A17.3-Legislation-Protecting-the-Archaeological-Heritage-Resources.pdf [PDF]
- Appendix-A17.4-Legislation-Protecting-the-Architectural-Heritage-Resources.pdf [PDF]
- Appendix-A17.5-Impact-Assessment-and-the-Cultural-Heritage-Resource.pdf [PDF]
- Appendix-A17.6-Mitigation-Measures-and-the-Cultural-Heritage-Resource.pdf [PDF]
- Chapter 18 Material Assets
- Chapter 2 The EIA Process
- Chapter 21 Cumulative Effects and Interactions
- Chapter 3 Consideration of Reasonable Alternatives
- Chapter 4 Proposed Project Description
- Chapter 5 Construction & Commissioning
- Chapter 6 Noise & Vibration
- Chapter 7 Traffic & Transport
- Chapter 8 Biodiversity
- Appendix-A8.1-Parteen-Basin-Habitat-Assessment.pdf [PDF]
- Appendix-A8.10-Lepidoptera-Survey-Report.pdf [PDF]
- Appendix-A8.11-Vertigo-Survey-Report.pdf [PDF]
- Appendix-A8.12-Parteen-Basin-Mollusc-Survey-Report.pdf [PDF]
- Appendix-A8.13-Water-Treatment-Plant-Mollusc-Survey-Report.pdf [PDF]
- Appendix-A8.14-Watercourse-Crossing-Data.pdf [PDF]
- Appendix-A8.15-National-Research-Programme-Lakes-2016-Parteen-Basin-(Lower-Lough-Derg),-Inland-Fisheries-Ireland-Report.pdf [PDF]
- Appendix-A8.16-National-Research-Programme-Lakes-2016-Lough-Derg,-Inland-Fisheries-Ireland-Report.pdf [PDF]
- Appendix-A8.17-Aquatic-Ecological-Survey-at-the-Proposed-Parteen-Basin-Abstraction-Site-(August-2017).pdf [PDF]
- Appendix-A8.18-Aquatic-Ecological-Survey-at-the-Proposed-Parteen-Basin-Abstraction-Site-(August-2019).pdf [PDF]
- Appendix-A8.19-Aquatic-Invasive-Species-Survey-Report-2021.pdf [PDF]
- Appendix-A8.2-Assessment-of-the-Woodland-Near-Parteen-Weir.pdf [PDF]
- Appendix-A8.20-Underwater-Noise-Modelling-Report.pdf [PDF]
- Appendix-A8.21-Breeding-Bird-Summary-Report.pdf [PDF]
- Appendix-A8.22-Winter-Bird-Summary-Report.pdf [PDF]
- Appendix-A8.23-Aquatic-Invasive-Species-and-Macrophyte-Survey-at-Lough-Derg-and-Parteen-Basin.pdf [PDF]
- Appendix-A8.24-Bat-Derogation-Licence-Application.pdf [PDF]
- Appendix-A8.25-Otter-Derogation-Licence-Application-Final.pdf [PDF]
- Appendix-A8.3-Site-Description-of-Coagh-Upper-Fen,-County-Offaly.pdf [PDF]
- Appendix-A8.4-Targeted-Habitat-Surveys-Report.pdf [PDF]
- Appendix-A8.5-Rare-Plant-Surveys-Report.pdf [PDF]
- Appendix-A8.6-Fungi-Survey-Report.pdf [PDF]
- Appendix-A8.7-Lichen-Survey-Report.pdf [PDF]
- Appendix-A8.8-Bryophyte-Survey-Report.pdf [PDF]
- Appendix-A8.9-Bat-Surveys-Report.pdf [PDF]
- Chapter 9 Water
- Appendix-A9.1-Abstraction-Assessment.pdf [PDF]
- Appendix-A9.2-Pipeline-Assessment.pdf [PDF]
- Appendix-A9.3-Non-linear-Principal-Infrastructure-and-38kV-Uprate-Works-Assessment.pdf [PDF]
- Appendix-A9.4-Flood-Risk-Assessment.pdf [PDF]
- Appendix-A9.5-Baseline.pdf [PDF]
- Appendix-A9.6-Laboratory-Analysis-and-In-Situ-Results.pdf [PDF]
- Appendix-A9.7-EPA-Monitoring-Information.pdf [PDF]
- Water Status Impact Assessment Report
- Application Documents
- Commission Documents
- Third Party Documents
- Invalid Submissions
- Invalid Submission - Frieda Keane Carmody.pdf [PDF]
- Invalid Submission - Cloughjordan Community Development Association CLG (SID-OBS-004617).pdf [PDF]
- Invalid Submission - Cloughjordan Community Development Association CLG (SID-OBS-004647).pdf [PDF]
- Invalid Submission - Cloughjordan Community Development Association CLG.pdf [PDF]
- Invalid Submission - Gráinne Kelly.pdf [PDF]
- Invalid Submission - June Kirwan.pdf [PDF]
- Invalid Submission - Kate Buddy O'Regan.pdf [PDF]
- Invalid Submission - Maurice Leamy.pdf [PDF]
- Invalid Submission - Michael Farrell.pdf [PDF]
- Invalid Submission - People Before Profit.pdf [PDF]
- Invalid Submission - River Shannon Environmental Protection Alliance Company Ltd.pdf [PDF]
- Invalid Submission - Sabrina Joyce-Kemper.pdf [PDF]
- Invalid Submission - Sheila O'Connor.pdf [PDF]
- Invalid Submission - Stephen Deegan.pdf [PDF]
- Invalid Submission - T.J. Scully.pdf [PDF]
- Invalid Submission - Wild Ireland Defence CLG.pdf [PDF]
- Submissions
- Submission - A.M.R Limited - 25.02.26.pdf [PDF]
- Submission - An Taisce - 25.02.26.pdf [PDF]
- Submission - Ballymore Eustace Trout and Salmon Anglers' Association - 05.02.26.pdf [PDF]
- Submission - Brian Farrell - 10.02.26.pdf [PDF]
- Submission - Brian Leddin - 24.02.26.pdf [PDF]
- Submission - Bridget Ginnity - 18.02.26.pdf [PDF]
- Submission - Carol Killeen - 25.02.26.pdf [PDF]
- Submission - Carol-Anne Murphy - 25.02.26.pdf [PDF]
- Submission - Caroline & Mark Eldridge - 24.02.26.pdf [PDF]
- Submission - Castleconnell Boat Club - 25.02.26.pdf [PDF]
- Submission - Castleconnell River Association (CRA) - 25.02.26.pdf [PDF]
- Submission - Chambers Ireland - 24.02.26.pdf [PDF]
- Submission - Christopher Campion - 24.02.26.pdf [PDF]
- Submission - Cllr Fiona Bonfield, Alan Kelly TD, & Cllr Louise Morgan Walsh - 25.02.26.pdf [PDF]
- Submission - Cllr Rita McInerney - 23.02.26.pdf [PDF]
- Submission - Cllr Seán Hartigan - 23.02.26.pdf [PDF]
- Submission - Cllr. Dr. Phyll Bugler - 25.02.26.pdf [PDF]
- Submission - Cllr. Séamie Morris - 25.02.26.pdf [PDF]
- Submission - Danny Janssens - 05.02.26.pdf [PDF]
- Submission - Derg Open Water Swim School & Lively Wimmin Swimmin - 25.02.26.pdf [PDF]
- Submission - Development Applications Unit - 25.02.26.pdf [PDF]
- Submission - Diarmuid O'Crowley - 25.02.26.pdf [PDF]
- Submission - Dr. John Galvin - 23.02.26.pdf [PDF]
- Submission - Dublin Chamber - 25.02.26.pdf [PDF]
- Submission - Eamonn Dooley - 24.02.26.pdf [PDF]
- Submission - Edward Frayne - 25.02.26.pdf [PDF]
- Submission - Eileen Mc Namara - 25.02.26.pdf [PDF]
- Submission - EirGrid - 25.02.26.pdf [PDF]
- Submission - Environmental Protection Agency - 24.02.26.pdf [PDF]
- Submission - Environmental Trust Ireland - 25.02.26.pdf [PDF]
- Submission - Eric Conroy - 25.02.26.pdf [PDF]
- Submission - Eva Killeen - 24.02.26.pdf [PDF]
- Submission - Fergal Hayes - 24.02.26.pdf [PDF]
- Submission - Fight the Shannon Pipeline Petition - 29.01.26.pdf [PDF]
- Submission - Fintan Dunne - 24.02.26.pdf [PDF]
- Submission - Fonsell Ltd - 18.02.26.pdf [PDF]
- Submission - Friends of the Irish Environment - 25.02.26.pdf [PDF]
- Submission - Futureproof Clare Environmental CLG - 25.02.26.pdf [PDF]
- Submission - Fáilte Ireland - 25.02.26.pdf [PDF]
- Submission - Garrett O'Neill - 25.02.26.pdf [PDF]
- Submission - Garrett Reil and Cliona Geary - 25.02.26.pdf [PDF]
- Submission - Geological Survey Ireland - 16.02.26.pdf [PDF]
- Submission - Gordon Beattie and Leslie Beattie - 06.02.26.pdf [PDF]
- Submission - HSA - 13.01.26.pdf [PDF]
- Submission - Ibec - 25.02.26.pdf [PDF]
- Submission - Inland Fisheries Ireland - 23.02.26.pdf [PDF]
- Submission - James Crowley - 25.02.26.pdf [PDF]
- Submission - James Cullen Snr. - 24.02.26.pdf [PDF]
- Submission - James Waldron (Agent = Corr Property Consultants Ltd.) - 16.02.26.pdf [PDF]
- Submission - James Waldron (Agent = McEnteggart Consultancy) - 16.02.26.pdf [PDF]
- Submission - Joanne Skehan - 24.02.26.pdf [PDF]
- Submission - Joe Mayo - 24.02.26.pdf [PDF]
- Submission - John & Georgina Ringrose - 24.02.26.pdf [PDF]
- Submission - John Baker - 25.02.26.pdf [PDF]
- Submission - John Fingleton - 24.02.26.pdf [PDF]
- Submission - John Hensey - 19.02.26.pdf [PDF]
- Submission - John Quinn & Sandra Frayne - 25.02.26.pdf [PDF]
- Submission - John Sadlier - 25.02.26.pdf [PDF]
- Submission - Judith Kohler - 16.02.26.pdf [PDF]
- Submission - Keith Ball - 25.02.26.pdf [PDF]
- Submission - Kieran O'Connor - 24.02.26.pdf [PDF]
- Submission - Killaloe Ballina District Angler's Association - 25.02.26.pdf [PDF]
- Submission - Laois County Council - 25.02.26.pdf [PDF]
- Submission - Laura Kavanagh - 25.02.26.pdf [PDF]
- Submission - Liam Minehan - 25.02.26.pdf [PDF]
- Submission - Lough Derg Mermaids - 25.02.26.pdf [PDF]
- Submission - Lucy Murphy - 25.02.26.pdf [PDF]
- Submission - Mark Kinsella - 25.02.26.pdf [PDF]
- Submission - Martina Mangan - 16.02.26.pdf [PDF]
- Submission - Mattie McGrath TD - 23.02.26.pdf [PDF]
- Submission - McKeogh's Hardware Ltd - 25.02.26.pdf [PDF]
- Submission - Melina Sharp & Michael Eversen - 25.02.26.pdf [PDF]
- Submission - Melissa Anne Kenny - 19.01.26.pdf [PDF]
- Submission - Michael and Mary Kinsella - 25.02.26.pdf [PDF]
- Submission - Michael Barker & Company - 25.02.26.pdf [PDF]
- Submission - Michael Hoey - 25.02.26
- Submission - Michael Hoey - 25.02.26.pdf [PDF]
- Submission - Michael Hoey - Appendices
- 1715 2 Geo 1 Chapter 12 To encourage the draining and improving of bogs.pdf [PDF]
- Cover letter to ABP 2026.pdf [PDF]
- exhibit Brendan Slattery joins Barry Doyle 2013 -profile from web site.pdf [PDF]
- exhibit 2 b. John McKeown and the closure of the Barrow Navigation.pdf [PDF]
- exhibit MH 1 g. Arthur Cox & Procedure for Provisional Order.pdf [PDF]
- exhibit MH 25 Extract of the Memorandum of Understanding -(Appendix 8 of the Memorandum).pdf [PDF]
- exhibit -MH single photo of dredging at Gas pipe for document.pdf [PDF]
- exhibit M H 2 f Yevonne Scannell & Arthur Cox + to Nicholas O'Dwyer May 2002 -breakdown of my objection.PDF [PDF]
- exhibit M H 9 Section 68 of the Charter for the Royal and Grand Canals.pdf [PDF]
- exhibit MH 1 a Interference Notice 10 March 2003.pdf [PDF]
- exhibit MH 1 N Notification to Commercial Boat Operators - Navigation authorities for the purposes of section 21 of the WSA 1942.PDF [PDF]
- exhibit MH 7 b Letter from Waterways Ireland 9th August 2002 acknowledging formal notification of abstractions No 2 and 7.PDF [PDF]
- exhibit MH 1 Interference Notice no 1 -18 Jan 2002.pdf [PDF]
- exhibit MH 1 b. Canalways Ireland Interference Notice 10 03 2003 & Parrallel strand.PDF [PDF]
- exhibit MH 1 d An Taisce Interference Notice - 20 day of June 2003.pdf [PDF]
- exhibit MH 1 e. Petition of Michael Hoey to ABP - Boyne abstraction 2003 -Meath Eastern Regional Water Supply Provisional Order CW0502.PDF [PDF]
- exhibit MH 1 f Navigation Authority & Arthur Cox advice to Council.pdf [PDF]
- Exhibit MH 1 h Requesting Uisce Eireann to be Notified of proposal for Water Supply Project 2025 under section 21 of the WSA.PDF [PDF]
- exhibit MH 1 i. photos of dredging at Gas Pipe with boat stuck above.pdf [PDF]
- exhibit MH 1 J. Formal Notice to Navigation Authorities 19 Feb 2003.pdf [PDF]
- exhibit MH 1 k . letter of 19 Feb 2003 from KCC highlighting the need to issue an Interference Notice.PDF [PDF]
- exhibit MH 1 L ABP to Taidgh O'Cruadalaoicht stating that KCC said that 'it is not proposed to abstract water at Kildare Town.PDF [PDF]
- exhibit MH 1 m Notification to 9 Commercial operators.pdf [PDF]
- Exhibit MH 1 p - Pumping water .log [LOG]
- Exhibit MH 1 p - Pumping water for the Royal Canal at the Boyne Aquaduct 31 August 2025.pdf [PDF]
- Exhibit MH 12 ABP & No legslative provision to allow adjudication on Ancillary works.pdf [PDF]
- exhibit MH 14 EPA & Draft of Barrow Navigation & Waterways Ireland's responsibility.pdf [PDF]
- exhibit MH 14 a Waterways Ireland to MH - KCC to provide a new source for the Grand Canal.pdf [PDF]
- exhibit MH 14 b Nicholas O'Dwyer to John McKeown of WI re an additional 300 mm to draft of Barrow navigation.PDF [PDF]
- exhibit Mh 14 c Mr EIS - Conor Skehans advice to EPA and carrying our EIA 15 08 00.pdf [PDF]
- exhibit MH 14 d Report of Mr Dom Hegarty to ABP on the Barrow Abstraction proposal & the draft of the Barrow Navigation.PDF [PDF]
- exhibit MH 15 Komex Report on the Kildare Water Strategy.pdf [PDF]
- exhibit MH 16 MH submission on Bord Na Mona & substitute consent for historic peat removal.pdf [PDF]
- exhibit MH 16 a, Duchas submission to EPA re Daingean Rathdrum bog, 27 September 1999.pdf [PDF]
- Exhibit MH 2 ABP & No legslative provision to allow adjudication on Ancillary works.pdf [PDF]
- exhibit MH 2 a Table 1. abstractions from the Barrow catchment (last Updated 13 07 2015).pdf [PDF]
- exhibit MH 2 ABP dont do cumulative effects in 2003.pdf [PDF]
- exhibit MH 2 c extract from the conservation Plan for Pollardstown Fen P 37 draft 1.pdf [PDF]
- exhibit MH 2 d Letter to Waterways Ireland 05 08 2002 notifying them of seven proposed abstractions 004.PDF [PDF]
- exhibit MH 2 e Letter from Waterways Ireland 9th August 2002 acknowledging formal notification of abstractions No 2 and 7.PDF [PDF]
- exhibit MH 24 Provisional Order 151 CA 2004 Justice Abbot's Order 26th May 2005.pdf [PDF]
- exhibit MH 25 a. Carbal Report - 2007 Carbon gas balances in industrial cutaway for Bord Na Mona.PDF [PDF]
- exhibit MH 3 Letter to Irish Water 24th January 2022.pdf [PDF]
- exhibit MH 4 Class 35 A & B Planning Exemption Regs 2024.pdf [PDF]
- exhibit MH 5 Navigation Authority - UK Land Drainage Act 1930.pdf [PDF]
- exhibit MH 6 ACP have no new procedures and are prohibited from adjudicating on section 21 of WSA.PDF [PDF]
- exhibit MH 7 a Brendan slattery UCC - LA Water supply 2005 -source.pdf [PDF]
- exhibit MH 7 Arthur Cox denying my status.pdf [PDF]
- exhibit MH 8 Liam Cashman 12 Jan 2005 explaining the Need to assess the strategic needs if drawing from the same source.PDF [PDF]
- exhibit MH 8 a 04 02 2025 Response from Irish Water Uisce Eireann - alternatives considered bones of email.PDF [PDF]
- exhibit MH 8 letter from Liam Cashman European Commission.pdf [PDF]
- exhibit MH 9 March 2003 ABP clarify that there was no communications between the EPA & ABP.pdf [PDF]
- exhibit MH 9 a Charter - & extract from The Canals of the South of Ireland -Ruth Delaney.pdf [PDF]
- Interference Notice 2026 the Water Supply Project 2025 -final 24 02 2026.pdf [PDF]
- List of exhibits and their status 24 02 2026.pdf [PDF]
- Water Supplies Act of 1942.pdf [PDF]
- Submission - Michael McKeogh - 11.02.26.pdf [PDF]
- Submission - Michael Reidy - 20.02.26.pdf [PDF]
- Submission - Michelle Keary - 23.02.26.pdf [PDF]
- Submission - Michelle McNamara - 25.02.26.pdf [PDF]
- Submission - Mountshannon Community Council - 25.02.26.pdf [PDF]
- Submission - National Office for Environmental Health Services - 25.02.26.pdf [PDF]
- Submission - National Transport Authority - 25.02.26.pdf [PDF]
- Submission - Office of Public Works - 23.02.26.pdf [PDF]
- Submission - Pamela Quirke O'Meara - 24.02.26.pdf [PDF]
- Submission - Peamount Healthcare - 25.02.26.pdf [PDF]
- Submission - Port Omna Beo - 25.02.26.pdf [PDF]
- Submission - Portumna & District Angling & Boatimg Association - 25.02.26.pdf [PDF]
- Submission - Richard Cahill - 19.02.26.pdf [PDF]
- Submission - River Shannon Environmental Protection Alliance Company Ltd - 24.02.26.pdf [PDF]
- Submission - Robert Frayne - 25.02.26.pdf [PDF]
- Submission - Samuel Norris - 25.02.26.pdf [PDF]
- Submission - Sarah Conroy - 25.02.26.pdf [PDF]
- Submission - Seamus Cullen - 25.02.26.pdf [PDF]
- Submission - Senator Dee Ryan - 25.02.26.pdf [PDF]
- Submission - Shane Mathews - 16.02.26.pdf [PDF]
- Submission - St. Flannans Fishing Club - 24.02.26.pdf [PDF]
- Submission - Stefan and Olivia Hahne - 22.02.26.pdf [PDF]
- Submission - Suzanne Noble - 24.02.26.pdf [PDF]
- Submission - Terry Forristal - 23.02.26.pdf [PDF]
- Submission - The Heritage Council - 24.02.26.pdf [PDF]
- Submission - The Local Authority Waters Programme (LAWPRO) - 25.02.26.pdf [PDF]
- Submission - The Lough Derg Anglers Association - 25.02.26.pdf [PDF]
- Submission - Tom & Mary Scully - 25.02.26.pdf [PDF]
- Submission - Tony O Brien - 23.02.26.pdf [PDF]
- Submission - Transport Infrastructure Ireland 20.02.26.pdf [PDF]
- Submission - Waterways Ireland - 25.02.26.pdf [PDF]
- Submission - William Lawrence Hodges - 24.02.26.pdf [PDF]
- Submission - Yvonne Moloney - 12.02.26.pdf [PDF]
- Submission - Éadaoin Kiely & Darren Kirwan - 24.02.26.pdf [PDF]
- Invalid Submissions
- Applicant Documents
- View associated documents
Observations on the application or appeal can be lodged within the appropriate time period here.
Legend
- Live Case
- Granted
- Refused
- Invalid
- Withdrawn
- See Case for further detail
Firefox
Safari
Chrome
Opera
Edge