Offshore Renewable Energy Projects

Offshore Renewable Energy (ORE) Projects

Overview of Current Status of Phase 1 ORE Applications 

Project ACP Reference Received Current Status Timeline
Oriel Wind Farm ABP-319799-24 24 May 2024 Request for further information dated 10 April 2025. Response received 16 January 2026. FI Response deemed significant and notices published inviting further submissions up to 13 May 2026.
Arklow Bank Wind Park 2 ABP-319864-24 6 June  2024 Request for further information dated 10 April 2025. Response received 10 April 2026. With the Commission for consideration.
North Irish Sea Array (NISA) ABP-319866-24 7 June 2024 Request for further information dated 10 April 2025 allowing response by 14 August 2026 (extended from 19 January 2026 at request of applicant). With the applicant, consideration of application paused until response to FI submitted.
Codling Windpark ABP-320768-24 6 September 2024 Request for further information dated 1 August 2025 allowing response by 30 June 2026 (extended from 11 May 2026 at request of applicant). With the applicant, consideration of application paused until response to FI submitted.
Dublin Array ABP-321992-24 28 February 2025 Request for further information dated 8 December 2025 allowing response by 17 September 2026. With the applicant, consideration of application paused until response to FI submitted.