Overview of Current Status of Phase 1 ORE Applications
| Project | ACP Reference | Received | Current Status | Timeline |
|---|---|---|---|---|
| Oriel Wind Farm | ABP-319799-24 | 24 May, 2024 | Request for further information dated 10 April 2025. Response received 16 January, 2026. | FI Response deemed significant and notices published inviting further submissions up to 13 May, 2026. |
| Arklow Bank Wind Park 2 | ABP-319864-24 | 6 June, 2024 | Request for further information dated 10 April 2025. Response received 10 April, 2026. | FI Response deemed significant and notices published inviting further submissions up to 29 July, 2026. |
| North Irish Sea Array (NISA) | ABP-319866-24 | 7 June, 2024 | Request for further information dated 10 April 2025 allowing response by 14 August, 2026 (extended from 19 January, 2026 at request of applicant). | With applicant, consideration of application paused until response to FI submitted. |
| Codling Windpark | ABP-320768-24 | 6 September, 2024 | Request for further information dated 1 August 2025. Response received 5 June, 2026. | With Commission for consideration. |
| Dublin Array | ABP-321992-24 | 28 February, 2025 | Request for further information dated 8 December 2025 allowing response by 17 September, 2026. | With applicant, consideration of application paused until response to FI submitted. |