Overview of Current Status of Phase 1 ORE Applications 

Project ACP Reference Received Current Status Timeline
Oriel Wind Farm ABP-319799-24 24 May, 2024 Request for further information dated 10 April 2025. Response received 16 January, 2026. FI Response deemed significant and notices published inviting further submissions up to 13 May, 2026.
Arklow Bank Wind Park 2 ABP-319864-24 6 June, 2024 Request for further information dated 10 April 2025. Response received 10 April, 2026. FI Response deemed significant and notices published inviting further submissions up to 29 July, 2026.
North Irish Sea Array (NISA) ABP-319866-24 7 June, 2024 Request for further information dated 10 April 2025 allowing response by 14 August, 2026 (extended from 19 January, 2026 at request of applicant). With applicant, consideration of application paused until response to FI submitted.
Codling Windpark ABP-320768-24 6 September, 2024 Request for further information dated 1 August 2025. Response received 5 June, 2026. With Commission for consideration.
Dublin Array ABP-321992-24 28 February, 2025 Request for further information dated 8 December 2025 allowing response by 17 September, 2026. With applicant, consideration of application paused until response to FI submitted.