5. Strategic Infrastructure Applications (Private Entities and Statutory Undertakers) Received in 2018
47 number wind turbines, Co. Kildare and Co. Meath. |
Permanent continuance of use of the existing 8,840 space long-term car park, Dublin Airport, Co. Dublin. |
Port capacity extension, Foynes, Co. Limerick. |
Ringsend wastewater treatment plant upgrade project including a regional biosolids storage facility, Dublin 4 and Dublin 11. |
Greater Dublin Drainage Project, Fingal County and Dublin City. |
Construction of a new 220kV substation compound, Clonee, Co. Meath. |
An 110kV electrical substation, Upperchurch, Co. Tipperary. |
Wastewater Treatment Plant, Arklow, Co. Wicklow. |
Permanent continuation of use of the existing long-term car park, Swords Road (Old Airport Road), Santry, Co. Dublin. |
Electrical substation and infrastructure to connect solar PV generation, Clongeen, Co. Wexford. |
25 number wind turbines, Ardderroo, Letter and Finnaun, County Galway. |
Continued operation of peat-fuelled power station to facilitate the phased transition to exclusive firing with biomass, Shannonbridge and Derrylahan, Co. Offaly. |
Disposal, treatment and recovery of waste, Flemingstown, Navan, County Meath. |
Electrical substation at Timahoe East, Co. Kildare. |