An Bord Pleanála Tagairt an cháis: PL09.320789
Cásuimhir an Údaráis Phleanála: 2460494
Maynooth 220kV Substation, Taghadoe and Windgates, Maynooth, Co. Kildare
Comhairle Contae Chill Dara
Cur síos
Construction of two Gas Insulated Switchgear (GIS) buildings and all ancillary works including associated temporary works at construction stage. Planning permission is sought for a period of 10 years. Natura Impact Statement submitted with the application.
Cineál Cáis
Achomharc Pleanála
Cinneadh
Contribution Appeal Decided
Dáta an tsínithe
10/04/2025
TMTT
Níl
RTN
Níl
Páirtithe
-
EirGrid (Applicant)
-
EirGrid (1st Party Appellant) (Active)
Stair
-
10/04/2025
Contribution Appeal Decided
-
11/09/2024
Lodged