Bord Pleanála Tagairt an cháis: RL20.313557
Cásuimhir an Údaráis Phleanála: DED514
Rathleg, Castlerea, Co. Roscommon
Comhairle Contae Ros Comáin
Cur síos
Whether works consisting of proposed underground 10Kv grid connection to connect a permitted onsite solar farm substation to the existing 38Kv Castlrea substation is or is not development or is or is not exempted development
Cineál Cáis
Tarchur
Cinneadh
Is development and is exempted development
Dáta an tsínithe
19/10/2023
TMTT
Níl
RTN
Níl
Páirtithe
-
Elgin Energy Services Ltd (1st party Referrer)
-
Elgin Energy Services Ltd (1st party Referrer) (Active)
-
Michael and Maureen Larkin (Owner Occupier)
-
Martin Keane (Owner Occupier)
-
Michael and Maureen Larkin (Owner Occupier)
-
Martin Keane (Owner Occupier)
-
Michael and Maureen Larkin (Owner Occupier)
-
Martin Keane (Owner Occupier)
-
Michael and Maureen Larkin (Owner Occupier)
-
Martin Keane (Owner Occupier)
-
Michael and Maureen Larkin (Owner Occupier)
-
Martin Keane (Owner Occupier)
-
Michael and Maureen Larkin (Owner Occupier)
-
Martin Keane (Owner Occupier)
-
Michael and Maureen Larkin (Owner Occupier)
-
Martin Keane (Owner Occupier)
-
Michael and Maureen Larkin (Owner Occupier)
-
Martin Keane (Owner Occupier)
Stair
-
19/10/2023
Is development and is exempted development
-
11/05/2022
Lodged