Bord Pleanála Tagairt an cháis: PL17.317568
Cásuimhir an Údaráis Phleanála: 23458
Causetown, Platin, Drogheda, Co. Meath
Comhairle Contae na Mí
Cur síos
Upgrade of Gorman to Platin 110 kV overhead line (OHL) (19.76 km long and comprising 109 supporting structures) along with all associated site works.
Cineál Cáis
Achomharc Pleanála
Cinneadh
Case is due to be decided by 15/11/2023
TMTT
Níl
RTN
Níl
Páirtithe
-
EirGrid plc. (Applicant)
-
Celene Sheehy (3rd Party Appellant) (Active)
-
Carroll Brothers Investments Limited (3rd Party Appellant) (Active)
Stair
-
13/07/2023
Lodged