An Bord Pleanála Tagairt an cháis: PL04.318852
Cásuimhir an Údaráis Phleanála: 235486
Rahanisky, Killeendaniel, Monard, Co. Cork
Comhairle Contae Chorcaí
Cur síos
10 year permission and 40 year operation period for solar farm and underground grid connection and associated site works. Works to include installation of underground cables. These works will be in the jurisdiction of Cork County Council and Cork City Council. A concurrent planning application will be lodged with Cork City Council for the remainder of the underground cable along the public roads to allow connection to the Kilbarry 110kV Substation in Blackpool, Cork City under Section 34 of the Planning and Development Act 2000 (PDA)(as amended).
Cineál Cáis
Achomharc Pleanála
Cinneadh
Grant permission with revised conditions
Dáta an tsínithe
01/08/2024
TMTT
Níl
RTN
Níl
Páirtithe
-
Harmony Solar Cork Limited (Applicant)
-
Pat, Glynis and William Casey (3rd Party Appellant) (Active)
-
Ms. Sheila Hyde and Mr. Michael Twomey (3rd Party Appellant) (Invalid)
-
Ms. Sheila Hyde and Mr. Michael Twomey (3rd Party Appellant) (Active)
Stair
-
01/08/2024
Grant permission with revised conditions
-
15/01/2024
Lodged