An Bord Pleanála Tagairt an cháis: PO03.319151
Knockshanvo and adjacent townlands, Co. Clare.
Comhairle Contae an Chláir
Níl an léarscáil ann
Cur síos
Proposed windfarm development of approximately 9 no. wind turbines and all associated works including the provision of a dedicated looped grid connection to the existing 110kV Ardnacrusha substation or a dedicated 110kV connection to Drumline 110kV substation.
Cineál Cáis
Tuairim ar Sholúbthacht Phriobháideach
Cinneadh
Case is due to be decided by 26/06/2024
TMTT
Níl
RTN
Níl
Páirtithe
-
FuturEnergy Knockshanvo Designated Activity Company (Applicant)
-
FuturEnergy Knockshanvo Designated Activity Company (Invalid)
Stair
-
22/02/2024
Lodged