An Bord Pleanála Tagairt an cháis: VA06F.319422
Between the existing Woodland Substation, Batterstown, County Meath and the existing Belcamp Substation, Clonshaugh, Fingal, County Dublin, known as the ‘East Meath – North Dublin Grid Upgrade. https://www.eirgrideastmeathnorthdublin.ie/
Comhairle Contae Fhine Gall
Cur síos
Proposed development of a 400 kV underground cable
Cineál Cáis
Iarratas ar Fhorbairt Leictreachais
Cinneadh
Approve with Conditions
Dáta an tsínithe
05/02/2025
TMTT
Tá
RTN
Tá
Páirtithe
-
EirGrid (Applicant)
-
Eirgrid (Active)
-
EirGrid (Active)
Stair
-
05/02/2025
Approve with Conditions
-
28/03/2024
Lodged
Doiciméid
-
Board Meeting Record
-
Tá an t-iarratas seo faoi réir nós imeachta MTT.