Bord Pleanála Tagairt an cháis: PL08.319433
Cásuimhir an Údaráis Phleanála: 23574
Shronebeirne, Listowel, Co. Kerry
Comhairle Contae Chiarraí
Cur síos
Construction of a battery storage facility, two single storey substation/control buildings, landscaping works and all associated ancillary infrastructure necessary to facilitate the development. A Natura Impact Statement accompanies the application.
Cineál Cáis
Achomharc Pleanála
Cinneadh
Case is due to be decided by 06/08/2024
TMTT
Níl
RTN
Tá
Páirtithe
-
Fastnet Energy Storage Limited (Applicant)
-
Wild Ireland Defense CLG (3rd Party Appellant) (Active)
Stair
-
02/04/2024
Lodged