Bord Pleanála Tagairt an cháis: PL29S.248530
Cásuimhir an Údaráis Phleanála: 2354/17
ESB Depot, Jamestown Road, Inchicore, Dublin 8.
Comhairle Cathrach Bhaile Átha Cliath
Cur síos
2 storey 220kV Gas Insulated Switchgear building, 2 no. bunded 220kV transformer bays, removal of existing tower, construction of a boundary wall and 11 no. lightning protection rods.
Cineál Cáis
Achomharc Pleanála
Cinneadh
Contribution Appeal Decided
Dáta an tsínithe
01/09/2017
TMTT
Níl
RTN
Níl
Páirtithe
-
Eirgrid (Applicant)
-
Eirgrid (Appellant)
Stair
-
01/09/2017
Contribution Appeal Decided
-
17/05/2017
Lodged